MRO Tracker · Automotive and EV
A free public sample tracking new EV, battery cell and battery pack plants in India, with capacity, investment, build stage and an analyst note for each project. Need a full map of a segment? Ask us for a custom study.
12projects
5states
5commissioned
14 Nov 2026last reviewed
Lithium ion cell gigafactory, Phase I
- Capacity
- 6 GWh in Phase I; site designed for 12 GWh
- Investment
- About Rs 6,000 crore total project (company, July 2026)
- Commissioning
- Phase I commissioned 23 Sep 2026
- End use
- Cells for EVs and energy storage (NMC cylindrical, LFP prismatic)
- Stage
- Commissioned
MRO View: The plant is built; revenue now hinges on carmaker qualification. The company targets first commercial revenue in Q3 FY27, starting with LFP cells for three wheelers and stationary storage.
Lithium ion cell gigafactory
- Capacity
- 6 GWh phase; 2.5 GWh commissioned as of June 2026 (company)
- Investment
- Not disclosed
- Commissioning
- Balance of 6 GWh phase targeted by end June 2026 (company)
- End use
- Cells for in house scooters, outside automakers and Ola storage products
- Stage
- Commissioned
MRO View: The only ACC PLI winner with cells in production. The founder has guided capacity to 20 GWh by next year, which would also close the gap on its 20 GWh PLI award.
Battery cell gigafactory, first phase
- Capacity
- 20 GWh a year in the first phase
- Investment
- Not disclosed
- Commissioning
- Production expected in 2027 (company)
- End use
- Cells for EVs and energy storage
- Stage
- Under construction
MRO View: The largest cell plant under construction in India with a dated start. The 320 acre site gives Tata's vehicle business a captive cell source once qualification is done.
Giga 1 lithium ion cell line
- Capacity
- 2 GWh first line; 16 GWh planned at the site
- Investment
- Rs 9,500 crore for the Giga Corridor through 2031 (company)
- Commissioning
- 60 MWh qualification plant commissioned July 2026; Giga 1 commercial output in 2027
- End use
- NMC 2170 cylindrical cells, mainly for electric two wheelers
- Stage
- Under construction
MRO View: Validation samples started going to customers in August 2026. Bulk output is a 2027 event, so near term cell volumes stay small.
Battery giga factory (LFP)
- Capacity
- 40 GWh a year initially, scalable to 100 GWh
- Investment
- Not disclosed
- Commissioning
- Production ramp up in the second half of 2026 (FY26 annual report)
- End use
- Grid storage systems and packs first; cell making to follow
- Stage
- Under construction
MRO View: Civil works are complete and lines are being installed. Early output is aimed at grid storage, so its effect on vehicle battery supply will come later.
Factory 3.0, scooter and battery pack plant
- Capacity
- Phase 1 planned at 6.5 lakh units a year (raised from 5 lakh on 26 Oct 2026)
- Investment
- About Rs 2,000 crore (company, 2024)
- Commissioning
- Production start guided for October 2026; Phase 1 completion by March 2027
- End use
- Electric scooters and battery packs
- Stage
- Under construction
MRO View: Management says Ather could have sold 13,000 to 15,000 more scooters a month if supply allowed. The October capacity raise shows the plant is being sized for that gap.
Greenfield car and SUV plant for Tata and JLR
- Capacity
- 2.5 lakh vehicles a year at full ramp over five to seven years
- Investment
- Rs 9,000 crore
- Commissioning
- Operations began 9 Feb 2026
- End use
- EV, ICE and hybrid models for Tata Motors and JLR
- Stage
- Commissioned
MRO View: The plant opened with Range Rover Evoque assembly. Electric models for both brands are part of the planned mix as volumes build.
EV assembly plant and Phase 2 expansion
- Capacity
- 50,000 vehicles a year, being expanded to 1.5 lakh
- Investment
- USD 500 million in phase one; a further USD 500 million for buses and scooters
- Commissioning
- Local production began August 2025; Phase 2 investment approval received September 2026
- End use
- Electric SUVs now; electric buses and scooters planned
- Stage
- Commissioned
MRO View: Phase 2 moves the site beyond SUV kit assembly into buses and scooters.
Electric bus and truck plant
- Capacity
- 15,000 vehicles a year (10,000 buses, 5,000 trucks)
- Investment
- Rs 2,500 crore
- Commissioning
- Commercial production expected within 30 days of 22 Sep 2026 (company); start not yet confirmed
- End use
- Electric buses and heavy trucks, with on site battery pack assembly
- Stage
- Under construction
MRO View: The plant targets 500 to 1,000 vehicles in FY27, with trucks about 60% of output. Cells will be imported at the start.
New energy passenger vehicle plant
- Capacity
- Not disclosed
- Investment
- About Rs 14,000 crore (company, January 2026)
- Commissioning
- First SUV due to be unveiled 4 Dec 2026; production start not confirmed
- End use
- Plug in hybrids first; battery electric models from 2027
- Stage
- Under construction
MRO View: JSW is entering cars under its own brand, separate from its MG venture. The first product is a plug in hybrid, so pure EV volumes from this site are a 2027 question.
EV battery pack assembly plant
- Capacity
- 75,000 packs a year in phase one
- Investment
- Not disclosed
- Commissioning
- Commissioned January 2025
- End use
- NMC and LFP packs for Hyundai EVs made in India
- Stage
- Commissioned
MRO View: Pack assembly is local but cells are still imported. Hyundai has named Tamil Nadu its flagship EV hub, with a mass market dedicated EV due from Chennai.
Lithium ion and sodium ion cell plant
- Capacity
- 12.5 GWh (2.5 GWh first phase, 10 GWh second phase)
- Investment
- Rs 8,000 crore over five years
- Commissioning
- Not disclosed; MoU signed January 2024
- End use
- Cells for EVs and energy storage
- Stage
- Announced
MRO View: An early stage project at MoU level. It matters mainly as a domestic technology play, with silicon anode and sodium ion work in its pipeline.
All 12 projects at a glance
| Company | Project | State | Capacity | Stage |
|---|---|---|---|---|
| Exide Energy Solutions (Exide Industries) | Lithium ion cell gigafactory, Phase I | Karnataka | 6 GWh in Phase I; site designed for 12 GWh | Commissioned |
| Ola Cell Technologies (Ola Electric) | Lithium ion cell gigafactory | Tamil Nadu | 6 GWh phase; 2.5 GWh commissioned as of June 2026 (company) | Commissioned |
| Agratas (Tata Group) | Battery cell gigafactory, first phase | Gujarat | 20 GWh a year in the first phase | Under construction |
| Amara Raja Advanced Cell Technologies | Giga 1 lithium ion cell line | Telangana | 2 GWh first line; 16 GWh planned at the site | Under construction |
| Reliance New Energy | Battery giga factory (LFP) | Gujarat | 40 GWh a year initially, scalable to 100 GWh | Under construction |
| Ather Energy | Factory 3.0, scooter and battery pack plant | Maharashtra | Phase 1 planned at 6.5 lakh units a year (raised from 5 lakh on 26 Oct 2026) | Under construction |
| Tata Motors Passenger Vehicles | Greenfield car and SUV plant for Tata and JLR | Tamil Nadu | 2.5 lakh vehicles a year at full ramp over five to seven years | Commissioned |
| VinFast | EV assembly plant and Phase 2 expansion | Tamil Nadu | 50,000 vehicles a year, being expanded to 1.5 lakh | Commissioned |
| JSW Greentech (Ampstar) | Electric bus and truck plant | Maharashtra | 15,000 vehicles a year (10,000 buses, 5,000 trucks) | Under construction |
| JSW Motors | New energy passenger vehicle plant | Maharashtra | Not disclosed | Under construction |
| Hyundai Motor India with Mobis India | EV battery pack assembly plant | Tamil Nadu | 75,000 packs a year in phase one | Commissioned |
| GODI India | Lithium ion and sodium ion cell plant | Telangana | 12.5 GWh (2.5 GWh first phase, 10 GWh second phase) | Announced |
Need the numbers behind this tracker?
We map plants, capacity and supply chains for any EV or battery segment in India.