MRO Tracker · Chemicals
New chemical plants and capacity additions across India, from specialty and agro intermediates to polymers, fluorochemicals and pharma intermediates. Each entry shows the product, capacity, investment and build stage, with a short note from our analysts on what it means for buyers and suppliers.
This tracker is a free public sample of what we follow. For your product, we can map every announced project and competitor in India, as a report or a custom study. Ask us
15 of 15 projects
Chlorination and specialty chemicals plant
- Capacity
- Not disclosed
- Investment
- About Rs 300 crore (spent up to start of manufacturing)
- Commissioning
- Manufacturing started 29 Sep 2026
- End use
- Not disclosed
The subsidiary had spent about Rs 300 crore by the time manufacturing began at Dahej. Products, capacity and end markets have not been disclosed. The plant's effect on group margins depends on what it goes on to make. Read our news story
CPVC resin plant, in collaboration with Lubrizol Advanced Materials
- Capacity
- About 50,000 TPA (phase 1)
- Investment
- Not disclosed
- Commissioning
- Commercial production intimated 11 Aug 2026 (inaugurated 16 Jun 2026)
- End use
- Plumbing, water management, fire safety, industrial piping
The plant sits at Grasim's Vilayat chlor alkali unit, which was chosen for its captive chlorine. Phase 1 is 50,000 tonnes against an original plan of close to 100,000 tonnes built in phases, so phase 2 timing is the next thing to watch. Read our news story
Pesticide manufacturing unit (formulation plant)
- Capacity
- 23,000 TPA
- Investment
- Up to Rs 200 crore
- Commissioning
- Operational by Apr 2028
- End use
- Crop protection
Land at Nagpur is already acquired. The company linked the new site to the end of incentives at its Udhampur unit in March 2026 and expects better logistics. Management describes it as a largely automated formulation plant, not a technical synthesis unit.
Dual feed cracker with polyethylene and polypropylene units
- Capacity
- 1.2 MTPA cracker; 1 MTPA PE; 1 MTPA PP
- Investment
- Not disclosed separately (whole refinery and petrochemical complex over Rs 79,450 crore)
- Commissioning
- Q4 2026 (Q3 FY27); some capacity possibly Nov to Dec 2026
- End use
- Packaging and films, pipes, automotive, agriculture and raffia, fibres and non wovens
Two million tonnes of new PE and PP is a big addition to Indian polymer supply, and import prices could come under pressure once these lines run steadily. The refinery began commercial operations on 22 June 2026 after a fire delayed it.
Inorganic pigments: ultramarine blue, ultramarine violet, mixed metal oxides including bismuth vanadate
- Capacity
- 2,500 TPA per board approval (6,850 TPA in draft EIA)
- Investment
- Rs 250 crore per board approval (Rs 110 crore in draft EIA)
- Commissioning
- Phased over FY28 and FY29
- End use
- Paints, coatings, plastics, rubber, ceramics, inks, textiles, construction materials
The board approved Rs 250 crore for 2,500 tonnes, while the draft environmental report filed with the Tamil Nadu pollution board lists 6,850 tonnes at Rs 110 crore. Funding is a mix of internal accruals and term loans. Watch the final clearance to see which capacity figure holds.
HFO refrigerants and anhydrous hydrogen fluoride complex, with value added HF products
- Capacity
- 20,000 TPA HFOs; 30,000 TPA AHF
- Investment
- Rs 2,285 crore (revised from Rs 1,100 crore)
- Commissioning
- 28 Feb 2028 (Q4 FY28)
- End use
- Next generation refrigerants; value added hydrogen fluoride products
The board raised the budget from Rs 1,100 crore, approved in October 2024, to Rs 2,285 crore after a change in project scope. SRF cites expected demand for HFOs and value added hydrogen fluoride products, extending its fluorochemicals chain into next generation refrigerants.
Green PVC project: PVC, VCM and ethylene glycol, with carbide, acetylene and caustic soda units
- Capacity
- 2,000 KTPA PVC; 2,002 KTPA VCM; 400 KTPA ethylene glycol; 1,310 KTPA caustic soda (as cleared)
- Investment
- Not disclosed
- Commissioning
- All units targeted by 1 Oct 2027
- End use
- Not disclosed
The company's compliance report says construction is underway on the first polymerisation train, the VCM reactor area, the chlor alkali unit and the acetylene unit. It expects all units to start commercial operation by 1 October 2027 and says the PVC will serve the domestic market and reduce reliance on imports.
Contrast media intermediates, high intensity sweeteners and multipurpose chemistry
- Capacity
- Not disclosed
- Investment
- About Rs 2,300 crore; board approved Rs 1,000 crore over three to four years
- Commissioning
- FY29, built in phases
- End use
- Contrast media, sweeteners
Groundbreaking took place on 28 February 2026 on a 102 acre site planned for zero liquid discharge with marine discharge. The company says it has received Consent to Establish and started work with technical consultants. It has not disclosed products or capacity for the site itself.
Expansion of surfactants, fatty alcohol, erucic acid, glycerine, specialities and fermentation
- Capacity
- 30,000 TPA surfactants; 35,000 TPA fatty alcohol; 20,000 TPA erucic acid; 24,000 TPA glycerine; 21,000 TPA specialities; 1,500 TPA fermentation
- Investment
- Over Rs 750 crore
- Commissioning
- Over the next few years; several projects already started
- End use
- Home and personal care, oil and gas, food and beverages, lubricants, paints and coatings, agrochemicals, pharmaceuticals, rubber
The plan doubles fatty alcohol, erucic acid and glycerine capacity and triples specialities, supporting a goal of a US$1 billion global business before 2030. The company also plans to raise renewable energy use to 75 percent.
Chlorinated paraffin capacity expansion
- Capacity
- 14,000 TPA added
- Investment
- About Rs 15 crore
- Commissioning
- Commercial production by Jul 2028
- End use
- PVC compounds, industrial coatings, flame retardants, high performance lubricants
The company says the Kurnool plant is running at full capacity and demand is outpacing supply. Output from the new line is due in July 2028, with about Rs 100 crore a year of revenue expected at full scale. Until then, extra demand will have to be met by other suppliers. Read our news story
Pharmaceutical excipients: cellulose and starch based, including croscarmellose sodium and sodium starch glycolate
- Capacity
- 720 MT to 4,500 MT a year
- Investment
- About Rs 20 crore
- Commissioning
- Expansion completed; trial batches started Oct 2026; commercial production expected shortly
- End use
- Pharmaceutical and nutraceutical formulations
The Rs 20 crore expansion is funded through bank loans and internal accruals. The test now is how fast customer approvals turn trial batches into regular orders. Read our news story
Backward integrated ibuprofen unit
- Capacity
- 6,000 TPA added (12,000 to 18,000 TPA)
- Investment
- About Rs 350 crore
- Commissioning
- Dec 2027
- End use
- Pharmaceuticals (API)
Existing ibuprofen capacity runs at 95 percent utilisation, so this is demand led. The company describes itself as a leading global ibuprofen maker and will fund the Rs 350 crore cost from internal accruals. Read our news story
Dedicated specialty chemical plant under a long term tolling deal with a global chemical company
- Capacity
- Not disclosed
- Investment
- About Rs 35 crore
- Commissioning
- Q3 FY27
- End use
- Not disclosed
IOL will make one specialty chemical exclusively for an unnamed global customer that is not a related party. The company expects the deal to add materially to revenue once supplies start. Read our news story
Site 5, Phase 1: three large scale specialty chemical products
- Capacity
- Up to 16 production blocks possible; 2 running in Phase 1
- Investment
- Rs 1,500 to 1,600 crore planned over four years, mainly for Site 5 and a new R&D site
- Commissioning
- Commercial operations from 26 Jun 2026
- End use
- Pharmaceuticals and agrochemicals
Phase 1 starts with three large scale products, two for pharma and one for agro. Management said in May 2026 that validation batches were done and orders were in hand. With up to 16 blocks possible on the site, suppliers of reactors, utilities and solvents should expect more orders as later blocks come up.
Site 3++ for new molecules
- Capacity
- Not disclosed
- Investment
- Not disclosed
- Commissioning
- Commercial operation from 22 Feb 2026; ramp up through FY27
- End use
- Material science
Management links Site 3++ to growth in its material science business, which was 17 percent of sales. Deliveries from the site to Milliken began in April and May 2026, and the company expects the ramp up to continue in FY27.
No projects match these filters. Clear a filter to see more.